Works carried out on the rehabilitation and modernization of the tower block 6 – 215MW in TPP Tuzla
- Preparation of the construction site, which includes: the production of all the necessary ELRs and PPZs
- Dismantling existing filling stations
- Preparation of all surface RT3, RT4, RT5 which includes water jet cleaning under pressure of 600-1200 bar, if necessary and 2500 bar
- Injection of cracks
- Procurement and installation of wooden and metal structures for installation of fixed scaffolding and work platforms for sanitary and prefabrication works
- Making and mounting of lattice floor on main distribution channels
- Installation of PVC fillers
- Installing the supporting structure for mounting the drop eliminator and PE pipe
- Installation of pipe network for distribution of hot water from polyester pipes
- Installation of sprinklers on the pipe network for distribution of hot water
- Installation of droplet eliminators
- Procurement and installation of the valve control valve butterfly
- Installation of automation for remote control of the partition – regulating valve for charging the cooling system and regulation of the water level in the pool of cooled water
- Calibration (power control cables)
- Purchase and installation of remote control equipment for refilling the refrigeration system
- Purchase and installation of new hydraulic aggregates for the operation of plate seals