In June 2014, the Contract No. 194-TET / 14 was signed with the Public Enterprise of Elektroprivreda Bosne i Hercegovine d.d Sarajevo for “Making and delivering 8 pieces of coal mill types for coal type VML 260.62K for blocks 4 and 5 in TE Tuzla”. The implementation of the Contract is in progress and is now a mold molding phase. Delivery of the first impellers is expected at the end of September. All cars should be delivered by December 31, 2014.